I live in Dunedin, have a long-term health condition and rely on specialist appointments. I want to know what the new hospital will actually deliver for patients in Otago and Southland. I am considering my vote in the 2026 New Zealand general election. What is actually open and treating patients at the new Dunedin Hospital now, what is still being built or moved, and what are the expected dates for the different stages?
New Dunedin Hospital: what patients can expect by October 2026
For someone living in Dunedin who depends on specialist care, the key distinction is between services already treating patients, facilities still under construction, and services that have yet to transfer into the new hospital.
The new Dunedin Hospital is intended to serve patients across Otago and Southland, not just Dunedin. But a new building does not automatically mean every service is available there, that waiting lists will shorten, or that specialist appointments will become easier to obtain.
For your 2026 election decision, the useful questions are what is operational now, when the remaining clinical services are due to move, and whether the new facilities will deliver additional capacity or mainly replace existing facilities.
1. What is actually open now?
Outpatients | Whare Mātūtū
Open to patients
First patients: 12 October 2026
Inpatient hospital
Under construction
Expected to receive patients in 2031
As of 15 October 2026, the first new clinical building has started treating patients. Health New Zealand confirmed that the first appointments took place on Monday 12 October, following the building's official opening in August. First patients welcomed to New Dunedin Hospital outpatient buildingNew Dunedin Hospital outpatient building officially opens
Services in the new outpatient building
The five-storey building at 360 Cumberland Street, Dunedin brings together specialist outpatient appointments, diagnostic services and some procedures. The planned service mix includes:
- Specialist clinics, including children's and women's health.
- Orthopaedics, eye care (ophthalmology) and respiratory medicine.
- Medical imaging, including MRI, CT, X-rays and ultrasound.
- Day surgery, medical day-stay services, infusion services and procedure rooms.
- Physiotherapy and hand therapy.
New Dunedin Hospital outpatient building opens to patients on MondayCommunity open day at New Dunedin Hospital Outpatient BuildingGreat Day for South as Dunedin Hospital Outpatient Opens
An important qualification: the building being open does not mean every clinic listed above has already moved in or is operating at full capacity. Services are transferring in stages. Health New Zealand says patients should follow the location stated in their appointment letter, email or text, and contact their service if they are unsure. New Dunedin Hospital outpatient building opens to patients on MondayFirst patients welcomed to New Dunedin Hospital outpatient building
You can check the official New Dunedin Hospital project and service information.
2. What remains at the existing hospital?
The new outpatient facility is only the first stage of the overall rebuild. The current hospital on Great King Street remains essential to delivering hospital care.
The following major services are scheduled to transfer to the new inpatient building when it opens:
- Emergency department: emergency care continues at the existing hospital in the meantime.
- Inpatient wards: patients admitted to hospital will continue to use the existing facilities.
- Main surgical theatres: the principal inpatient surgical facilities remain at the current hospital for now.
- Intensive care and high-dependency care: these are planned for the new inpatient building, alongside expanded emergency and surgical facilities.
BreastCare, the New Zealand Artificial Limb Service, Gibson Day Unit, childcare and corporate functions are also among the services listed as remaining at the existing campus. Some are expected to remain there rather than transfer into the new inpatient building. New Dunedin HospitalNew Dunedin Hospital Inpatient Building begins to rise from the ground
In practical terms, the new outpatient building is not yet a replacement for the whole hospital. If you need emergency treatment, an overnight admission or an operation requiring the inpatient hospital, the existing hospital remains central to your care.
3. What are the expected dates for each stage?
The following timeline reflects the latest published project information available as of 15 October 2026.
Aug 2026
Outpatient building officially opened
28 August 2026
The building was formally opened, but clinical services had not yet begun seeing patients.
Oct 2026
Outpatient services begin operating
12 October 2026
First patients arrive. The staged transfer of clinics and services is under way.
Late 2026–early 2027
Remaining outpatient transitions
Staged transition
Health New Zealand's project information says some services will move after the initial opening, with further transitions expected by early 2027.
2026–2030
Inpatient building construction
Former Cadbury factory site
Structural steel construction is under way following the completion of major foundation works. The building will be linked to the outpatient facility by an overhead bridge.
2031
Inpatient hospital expected to receive patients
Second major stage
The expanded emergency department, inpatient wards, operating theatres, intensive care and high-dependency facilities are planned for this stage.
Sources: Health New Zealand's project timeline and July 2026 construction update. New Dunedin HospitalNew Dunedin Hospital Inpatient Building begins to rise from the groundNew Dunedin Hospital takes shape as steel goes up
One date distinction matters: 2030 is the scheduled practical-completion period for the inpatient building; 2031 is the expected start of patient care. The construction schedule is a target, not a guarantee. New Dunedin Hospital construction contract signedS E N S I T I V E
4. What additional treatment capacity is promised?
Health New Zealand says the outpatient facility, once fully staffed and operational, is expected to support the following additional activity each year:
13,300
Additional medical imaging appointments annually
Including planned diagnostic imaging such as MRI, CT and other scans.
1,700
Additional day-surgery procedures annually
Procedures that do not generally require an overnight hospital stay.
2,700
Additional medical day-stay appointments annually
For treatments and care that require attendance but not an overnight admission.
Source: Health New Zealand, August and October 2026 announcements. New Dunedin Hospital outpatient building opens to patients on MondayNew Dunedin Hospital Outpatient Building officially opened today
These are projected additional annual activities, not a report of treatments already delivered. The figures are conditional on the facility being fully staffed and operational.
For patients across Otago and Southland, the intended benefit is more diagnostic and planned-treatment capacity, improved facilities and a better flow between appointments and procedures. The government has also described the investment as supporting better access to specialist appointments and cancer care. New Dunedin Hospital Outpatient Building officially opened todayNew Dunedin Hospital outpatient building officially opens
There are limits to what these figures tell us, however:
- They do not specify how much waiting times will fall for a particular specialty.
- They do not establish how many additional specialist doctors, nurses or other clinicians will be recruited.
- They do not guarantee that every patient needing a scan, procedure or specialist consultation will receive it sooner.
- They do not represent the additional capacity of the entire completed hospital, which is still to come.
5. What does this mean for your care and your vote?
The new hospital has tangible benefits already beginning to reach patients, but the overall redevelopment is not finished. The most significant change for people needing emergency care, inpatient treatment or major surgery is still scheduled for 2031.
If you rely on regular specialist appointments, I would focus on three measurable questions when assessing parties' health policies in the run-up to the 2026 general election.
Will the new facilities translate into shorter waits?
Look for specific commitments and published performance measures for specialist first appointments, follow-up appointments, diagnostic imaging and elective treatment—not simply announcements about buildings.
Will the additional capacity have the staff to deliver it?
Ask what is planned for recruitment and retention of specialists, nurses, radiographers, technicians and other clinical staff, and how any staffing shortages will affect the promised extra activity.
How will patients be supported during the transition?
For people travelling from elsewhere in Otago and Southland, the location of appointments, transport and parking, coordination between services, and continuity of specialist care matter as much as the building itself.
These are questions to put to all parties, rather than assuming that the opening of a new building alone demonstrates improved access to healthcare.
6. Practical information for your next appointment
- New outpatient building: 360 Cumberland Street, Dunedin.
- Existing Dunedin Hospital and emergency department: 201 Great King Street, Dunedin.
- Outpatient building general enquiries: 03 474 0999.
- If your appointment is coming up: check your appointment letter, email or text for the correct building and clinic. Not every service has moved.
Health New Zealand's official outpatient information page provides directions, parking details, accessibility information and the current clinical services listed for the new building. New Dunedin Hospital Outpatients
Bottom line: as of October 2026, the outpatient building is open and treating patients, with specialist clinics, imaging and day procedures being delivered through a staged transition. The larger inpatient hospital—with its expanded emergency department, wards, operating theatres and intensive care facilities—is still being built, with patient care expected to begin in 2031. The key test for patients is whether the planned capacity is staffed and results in measurably better access to care.