We own a home on the Heretaunga Plains in Hawke's Bay and have school-age children. Flood risk, insurance and the cost of protecting our home are major concerns for us. I am considering my vote in the 2026 New Zealand general election. Which Hawke's Bay flood-protection works are already funded or underway, and which are still future options or election promises? Who is responsible for delivering each?
Hawke’s Bay flood protection: what is funded, what is being built, and what is still a proposal?
As at 30 October 2026, there is an important distinction for Heretaunga Plains homeowners: Hawke’s Bay has a substantial government-funded flood-protection programme already under construction, but that does not mean every part of the Plains will receive the same level of protection, or that all longer-term flood-risk solutions have been funded.
The central programme is the North Island Weather Events (NIWE) flood-resilience programme, established following Cyclone Gabrielle.
The headline funding
$256.5 million
Total Hawke’s Bay programme investment.
Central government
$209 million
Hawke’s Bay Regional Council
$47.5 million
Central government funding is managed through National Infrastructure Funding and Financing (NIFF). These are programme-wide figures, not money available for individual homeowners.
Restoring Flood ResilienceŌmāhu flood project reaches the finish line | News Archive
The Regional Council says all construction works in its community flood-resilience programme are intended to have begun by the end of 2026, with completion planned by mid-2027. Restoring Flood Resilience
1. Funded or already completed works on and around the Heretaunga Plains
These are the projects I would pay particular attention to as a Heretaunga Plains homeowner.
Completed Ōhiti Road | Ōmāhu flood-resilience project
- Main construction completed in August 2026.
- Cost: approximately $10 million.
- Built 2.1 km of new and upgraded stopbanks and bunds beside Ohiwia Stream.
- Raised approximately 800 metres of Ōhiti and Taihape roads.
- Includes drainage, culvert and erosion-protection improvements.
- Designed for a 1% Annual Exceedance Probability flood, with additional freeboard.
- Funding: 75% central government, 25% HBRC.
- Responsible: Hawke’s Bay Regional Council, with central government funding and local construction contractors.
This is a particularly significant example because 11 previously Category 2C homes had their classifications removed following the completed protection works. Ōmāhu flood project reaches the finish lineŌmāhu flood project reaches the finish line | News Archive
Completed Waiohiki stopbank
- A new one-kilometre stopbank along the Tūtaekurī River, from Napier Golf Course towards Redclyffe Bridge.
- Completed in May 2026.
- Designed to the 1% AEP standard.
- 45 properties previously classified Category 2C were moved to Category 1.
- Responsible: Hawke’s Bay Regional Council, working with landowners, mana whenua and contractors.
Waiohiki stopbank complete in major flood resilience milestone | News Archive
Under construction Pākōwhai flood-protection project
This is one of the more substantial projects for the Plains.
Pākōwhai sits between the Ngaruroro and Tūtaekurī river systems. The project is intended to provide an additional line of defence if existing river stopbanks are overwhelmed.
The planned works include:
- Approximately 5.5 km of stopbank and flood wall along the Tūtaekurī-Waimate Stream.
- Another approximately 3 km of stopbank and flood wall between Links Road and State Highway 2.
- Realignment of approximately 500 metres of the stream.
- A spillway to help manage excess water in a controlled manner.
- Additional 500 mm freeboard in the design.
The design uses the post-Cyclone Gabrielle flood modelling and targets a 1% AEP standard.
In July 2026, HBRC confirmed that 73 properties had their Category 2C classifications removed as construction advanced.
Funding and delivery:
- Funded through the NIWE programme.
- 75% central government and 25% HBRC.
- HBRC awarded the construction contract to Hick Bros Civil Construction in May 2026, with a contract value of approximately $18.23 million.
Responsible: HBRC is the project owner and delivery authority; Hick Bros is the construction contractor. PākōwhaiProgress for Pākōwhai: Homes cleared from Category 2C as protection works advance | WhirinakiGETS | Hawke's Bay Regional Council - HBRC Pākōwhai Southern Stopbank Flood Mitigation Tender
Under construction Ōmāhu (Chesterhope Upper) stopbank upgrade
This is separate from the completed Ōhiti Road | Ōmāhu project.
- Construction commenced in September 2026.
- Approximately 3 km of stopbank on the true-left bank of the Ngaruroro River will be raised and widened.
- The work runs from the Ohiwia/Okawa Stream downstream towards the State Highway 2 Ngaruroro River bridge.
- Designed against the post-cyclone 1% AEP flood standard.
- The Council expected completion by Christmas 2026.
Responsible: HBRC, through the NIWE-funded flood-protection programme. Construction underway on Ōmāhu stopbank upgrade | Ōmāhu stopbank upgradeRestoring Flood Resilience
Enabling works underway Brookfields Lower stopbank upgrade
This is important for the lower Heretaunga Plains, particularly around Meeanee and Awatoto.
- Approximately 3.6 km of stopbank along the Tūtaekurī River.
- Raising and strengthening existing sections.
- Reshaping the river-facing slope.
- Reviewing access ramps to reduce erosion and overtopping risks.
- Enabling works began in September 2026.
- Main construction was expected to begin in October 2026, with completion targeted for April 2027.
The upgrade responds to revised flood modelling following Cyclone Gabrielle, which identified that the existing stopbank was no longer meeting the required regional standard.
Responsible: HBRC, with Goodmans as the construction contractor. Brookfields Lower stopbank upgrade
2. Other funded regional projects
These are not all directly on the Heretaunga Plains, but they matter when assessing the wider regional flood-protection investment.
| Project | Position at October 2026 | Responsible |
|---|---|---|
| Havelock North | Construction underway | Hastings District Council |
| Whirinaki | Construction underway | HBRC |
| Pōrangahau | Construction underway in stages | HBRC |
| Waipawa stopbank | Construction about to begin | HBRC |
| Wairoa flood mitigation | Separate Crown-funded programme | HBRC |
| Pump station upgrades | Part of NIWE programme | HBRC |
| Regional telemetry improvements | Funded programme | HBRC |
A few important distinctions:
- Havelock North: This is delivered by Hastings District Council, rather than directly by HBRC, although it sits within the wider regional programme.
- Pōrangahau: Its northern flood-protection works are progressing, with additional southern-side protection being developed for the marae, urupā, Kaumātua Flats and private homes. The project has a stated budget of $13 million.
- Wairoa: Has a separate $70 million Crown funding allocation, rather than the normal 75:25 NIWE arrangement.
- Pump stations and telemetry: These are particularly important because flood protection depends on more than stopbank height. Drainage capacity, pumping and timely river-level information also matter.
Restoring Flood ResiliencePōrangahauHawke’s Bay Regional Council’s flood resilience programme on track as construction momentum builds | WaiohikiCyclone Recovery Funding Hawke's Bay
The important point is that this is not simply a collection of election announcements. There are actual government funding commitments, awarded construction contracts, completed works and projects with machinery already on site.
3. What is still a future option rather than funded construction?
This is arguably the most important part of the picture for someone considering their 2026 vote.
Reimagining the Heretaunga Plains flood-protection scheme
Future investment decisions
HBRC has been reviewing the long-term future of its two major flood-protection schemes:
- Heretaunga Plains Flood Control Scheme.
- Upper Tukituki Flood Control Scheme.
The project is called Reimagining Flood Resilience.
It considers whether the existing approach to flood protection should change, including:
- Whether stopbanks need to be raised, strengthened or extended.
- Whether additional floodways or other flood-management infrastructure are needed.
- How river management and drainage should be improved.
- How much protection communities should pay for.
- How to balance the cost of protection against the remaining flood risk.
The findings were presented to HBRC councillors on 29 July 2026, following an almost year-long community engagement process.
The Council says these findings will inform future decisions, including its 2027–2037 Long Term Plan.
This distinction matters: the review has happened, and recommendations have been developed, but that does not mean every recommended engineering project has an approved budget or construction timetable.
Responsible: HBRC, which owns and manages the regional flood-protection schemes. Community feedback helps shape the future of region's flood resilience | HomeReducing Flood Risk
Future strengthening of existing flood defences
The existing Heretaunga Plains scheme covers the low-lying areas associated with the Tūtaekurī, Ngaruroro and lower Tukituki rivers.
Much of the existing scheme is designed around the 1% AEP standard. Some densely populated areas have higher standards, including the Taradale stopbank upgrade, which has a 0.2% AEP design standard.
The Council's review recognises that the existing system needs to be reassessed against:
- Climate change.
- Changing river channels and riverbed levels.
- The consequences of extreme rainfall.
- The affordability of maintaining and improving protection.
The future level of investment is therefore a decision still to be made, rather than an automatic commitment to upgrade every part of the Plains.
August 2025Reducing Flood Risk
Further flood-scheme reviews and smaller infrastructure projects
HBRC is also reviewing 23 smaller flood-protection, drainage and river/stream schemes across Hawke’s Bay.
These reviews may identify further works, but they should not be confused with projects that already have committed construction funding.
Potential areas of improvement include:
- Drainage and pump capacity.
- Stopbank maintenance and strengthening.
- River-channel and gravel management.
- Vegetation management.
- Flood forecasting and warning systems.
The Council has also been working through 47 recommendations from the Hawke’s Bay Independent Flood Review, commissioned after Cyclone Gabrielle. Six initial priority projects were approved in December 2024.
Responsible: HBRC, working with district councils, mana whenua and central government where appropriate. Reducing Flood Risk
4. Who actually pays, and what does this mean for homeowners?
This deserves particular attention because a government-funded construction project does not necessarily mean homeowners escape the ongoing costs.
The existing Heretaunga Plains Flood Control Scheme had annual operating costs of approximately $5.5 million (excluding GST) in 2024–25.
Its funding arrangement was:
- 70% from targeted rates paid by scheme ratepayers.
- 30% from general rates and reserves.
The Regional Council has also indicated that some individual new flood-protection projects will have their own ongoing maintenance costs and rating arrangements.
For example, the Pōrangahau project is expected to cost approximately $63,000 annually to operate and maintain, with 70% coming from targeted rates and 30% from general rates.
For your household, there are three separate financial questions:
- Construction costs: Is the government paying for the initial infrastructure, or will local ratepayers have to contribute more?
- Ongoing costs: Who pays for inspection, repairs, pumping, stopbank maintenance and future upgrades?
- Residual property risk: Even after the works, will insurers consider the property insurable at reasonable premiums and excesses?
The third question is particularly important. A 1% AEP design standard does not mean a property is guaranteed protection from flooding. It describes the probability of a flood event of the design magnitude occurring in any given year.
It also does not automatically establish that every property behind the stopbank has the same flood exposure. Local drainage, groundwater, overland flow paths and the possibility of infrastructure failure all matter.
5. Who is accountable for delivery?
It helps to separate political funding decisions from the organisations actually responsible for the work.
| Organisation | Main responsibility |
|---|---|
| Central government | National funding commitments and policy |
| National Infrastructure Funding and Financing | Administration of the NIWE funding arrangements |
| Hawke’s Bay Regional Council | Regional flood schemes, engineering, project delivery, river management and maintenance |
| Hastings District Council | Delivery of the Havelock North project and local district responsibilities |
| Napier City Council | Local infrastructure and district responsibilities |
| Construction contractors | Physical construction under council contracts |
| Insurance companies | Individual property underwriting, premiums, exclusions and excesses |
An important accountability point: the Regional Council bears the cost of projects exceeding their allocated NIWE budgets under the programme arrangements described by HBRC. Restoring Flood ResilienceCyclone Recovery Funding Hawke's Bay
6. What should you look for in the 2026 general election?
I would distinguish between three things when assessing political claims.
- Existing commitments: Money already allocated, contracts awarded and work underway. These should not be presented as entirely new election promises.
- Future investment commitments: Additional funding for the 2027–2037 flood-protection programme, including the outcome of HBRC's Reimagining Flood Resilience work.
- New political promises: Any additional national funding, changes to insurance arrangements, household protection subsidies or new flood infrastructure that a party proposes.
I would particularly look for clear answers to the following questions.
| Issue | Question worth putting to candidates |
|---|---|
| Future flood protection | Will you fund additional Heretaunga Plains stopbank upgrades beyond the current NIWE programme? |
| Long-term funding | Will central government contribute to future major flood-protection improvements, or will local ratepayers carry the cost? |
| Insurance | What will you do about insurance affordability and availability in flood-exposed communities? |
| Household protection | Will there be assistance for property-level flood protection, such as barriers, drainage improvements and raising vulnerable infrastructure? |
| River management | What investment will be made in gravel management, river maintenance and flood capacity? |
| Climate resilience | Will you fund protection based on future climate conditions rather than simply restoring historical standards? |
| Accountability | Will you publish independent assessments of whether completed projects deliver their intended protection? |
These are questions about policy commitments, not assumptions about what any particular party will do.
7. The most useful documents to examine before voting
I would concentrate on these original sources rather than relying on campaign advertising.
Hawke’s Bay Regional Council
The most important source for actual construction progress and future regional plans.
July 2026 Reimagining Flood Resilience outcomes
Central government
Hawke’s Bay Flood Protection Works – legislation
Hastings District Council
My overall assessment
There is a meaningful amount of flood infrastructure being delivered across Hawke’s Bay, and the distinction between promises and actual construction is important.
For Heretaunga Plains residents, I would focus particularly on:
- The completed Ōhiti Road | Ōmāhu and Waiohiki works.
- The Pākōwhai flood-protection project.
- The Ōmāhu and Brookfields Lower stopbank upgrades.
- The outcome of the longer-term Heretaunga Plains flood-scheme review.
- Who will fund the next generation of improvements after the current government funding programme finishes.
One issue I would not overlook is the future cost of protection. Your children may live in the same house for decades. The important question is not just whether the current government has funded improvements, but whether there is a credible, affordable plan to maintain and progressively improve protection over the next 20–30 years.
And no flood scheme, however well engineered, eliminates the need for effective warnings and household evacuation planning.
A useful next step: I can also examine the Heretaunga Plains scheme in more depth, particularly the Ngaruroro, Tūtaekurī and Tukituki catchments, and separate the specific future engineering options from the projects already funded. That would help establish what protection your part of the Plains might realistically expect, rather than relying on region-wide announcements.